Progress of Construction
July 11, 2008 - April, 2009

Ground breaking for the new building for the Lenora Blackmore Branch took place on Friday, July 11, 2008. Dirt work started on Monday, July 14. The new building was built by Greg Frencken and houses both the Lenora Blackmore Branch Library and Greg Frencken Insurance. It is located at the northwest corner of Main and Benton streets in Windsor.

By September 9, 2008 the cement floor was in.

As of October 14, 2008 the exterior walls had been framed; by October 21, 2008 the roof was on and brick work began on December 9, 2008.

By February 17, 2009 all of the exterior brickwork was done, the entrance ramp and steps had been poured, the library's Book Drop was in place, and work on the interior walls and flooring was underway.

As of March 4, 2009 the sidewalks had been poured, the Henry County Library name was up on the building, with the interior painted and carpeting almost finished.

As of March 10, 2009 the carpeting is finished and some of the furniture has arrived.

The Grand Opening took place on May 27, 2009!!!!

July 11 - Ground Breaking:

July 15 - Out with the Old:

August 13 - Foundations are Ready:

September 3 - Smoothing out the base:

September 9 - The Floor is Done!:

September 16 - Starting on the Back Wall:

September 30 - The Dividng Wall Is In:

October 14 - The Outside Walls are Framed:

October 14 - A Peek Inside:

October 15 - Unloading a Roof Beam:

October 16 - Putting Up the Roof:

October 21 - The Roof is On:

October 21 - A View Inside:

December 9 - The Front Door is In:

And the first brick work is under way:

January 6 - The Alley brickwork is done!

And work is underway on the Benton Street side

January 13 - The Benton Street brickwork is about half done

And a closer view

February 17 - The library's brickwork is finished!

February 17 - All the exterior brickwork is done.

The entry ramp and steps have been poured

And the Book Drop is in place

February 24 - The Sidewalk is in

And our Name under the Lights!!

March 4 - Carpeting is almost done

And a view of the Storytime Room and Childrens' Corner

March 10 - Some of the futniture is here.

The Grand Opening of the new building occured at 10:00 a.m. on May 27, 2009!!


Library's Home Page Internet Access TACnet's Home Page
Send comments to: Webmaster, mike.good@henrycolib.org
URL: http://tacnet.missouri.org/hcl/WatchUsGrow2.html
Last modified: Wednesday, 24-Jun-2009 15:22:25 CDT